RoDTEP rate for HS code 73082011: For transmission line
Appendix 4R gives 7308 20 11, for transmission line, 1% of FOB value, uncapped.
Appendix 4R gives 7308 20 11, for transmission line, 1% of FOB value, uncapped.
Appendix 4R rates all 13 items under 7308 at 1%. Chapter 73 as a whole: all 250 rated, 0.5% to 1.5%. Duty is 15% on all 13 under 7308.
| Code | Description | Export rate | Duty |
|---|---|---|---|
| 7308 20 19 | Other | 1% | 15% |
| 7308 20 20 | Lattice masts | 1% | 15% |
| 7308 30 00 | Doors, windows and their frames and thresholds for doors | 1% | 15% |
| 7308 40 00 | Equipment for scaffolding, shuttering, propping or pit-propping | 1% | 15% |
| 7308 90 10 | Beams, channels, pillars and girders prepared for use in structures | 1% | 15% |
| 7308 90 20 | Drop rods | 1% | 15% |
| 7308 90 30 | Hatchway, rails and bulkheads for ships or boats and parts of hull | 1% | 15% |
| 7308 90 40 | Galvanised tension bars | 1% | 15% |
| 7308 90 50 | Structures and super structures for mining | 1% | 15% |
| 7308 90 60 | Truss rods | 1% | 15% |
| 7308 90 70 | Tubular steel poles for electric transmission and distribution lines | 1% | 15% |
| 7308 90 90 | Other | 1% | 15% |
| Level | Description |
|---|---|
| 73 | Articles of iron or steel |
| 7308 | Structures (excluding prefabricated buildings of heading 9406) and parts of structures |
| 7308 20 | Towers and lattice masts |
| 7308 20 11 | For transmission line (u) |
7308 20 11 at its First Schedule rate, no exemption applied; IGST per CBIC 045/2025, I229. How these are checked.
| Rate | Levy | Amount |
|---|---|---|
| 15% | Basic customs duty | ₹1,50,000 |
| 10% | Social Welfare Surcharge | ₹15,000 |
| 18% | IGST | ₹2,09,700 |
| 37.47% | Total | ₹3,74,700 |
0% for ASEAN countries takes ₹3,74,700 to ₹1,80,000, 2025 schedule.
Sources: Appendix 4R and 4RE, DGFT Notification 32/2024-25 as amended to 15/2026-27; the First Schedule to the Customs Tariff Act, 1975. Not an assessment or classification advice.
How RoDTEP rates are calculated7308 20 11 in the RoDTEP calculatorHow the import bill is built